Question 1
An owner is selecting a contract type for a fast-track petrochemical project where the full scope cannot be defined before construction begins. Which contract type places the MOST schedule risk on the owner?
- Lump Sum (Fixed Price)
- Time and Materials (T&M)
- Unit Price
- Guaranteed Maximum Price (GMP)
Show answer & explanation
Correct answer: B - Time and Materials (T&M)
Question 2
A project manager asks the scheduler to add a "Project Management" activity spanning the entire project duration so that PM labor costs can be tracked in the cost-loaded schedule. The scheduler should classify this activity as:
- A critical path task with its own predecessor and successor logic
- A milestone with assigned resource costs
- A Level of Effort (LOE) activity
- A summary/hammock activity tied to the first and last milestones
Show answer & explanation
Correct answer: C - A Level of Effort (LOE) activity
Domain 2: Application, Design, and Integration of Physical Security Systems 35% of exam
Question 3
A project network has the following Finish-to-Start activities:
• Activity A: Duration = 6 days, no predecessor
• Activity B: Duration = 4 days, predecessor = A
• Activity C: Duration = 9 days, predecessor = A
• Activity D: Duration = 3 days, predecessors = B and C
What is the total float of Activity B?
- 0 days
- 5 days
- 3 days
- 9 days
Show answer & explanation
Correct answer: B - 5 days
Question 4
A forensic schedule analyst needs to determine what the project completion date would have been in the absence of the owner's delays. The analyst has a validated as-built schedule and intends to remove the owner delay events one at a time from the as-built model. Which RP 29R-03 Method Implementation Protocol (MIP) is MOST appropriate?
- MIP 3.1 - As-Planned vs. As-Built
- MIP 3.6 - Impacted As-Planned
- MIP 3.7 - Time Impact Analysis
- MIP 3.8 - Collapsed As-Built
Show answer & explanation
Correct answer: D - MIP 3.8 - Collapsed As-Built
Question 5
At month 12 of a project, the following earned value data is reported: PV = $1,200,000; EV = $1,020,000; AC = $1,150,000; BAC = $3,000,000. Assuming future cost performance matches past performance, what is the Estimate at Completion (EAC)?
- $3,000,000
- $3,529,412
- $3,382,353
- $3,130,000
Show answer & explanation
Correct answer: C - $3,382,353
Question 6
During construction of an industrial facility, the owner issues a late design revision that redirects ductwork routing through a different building wing. This change adds 18 calendar days to the critical path. Under standard delay classification, this delay is BEST categorized as:
- Excusable and compensable, entitling the contractor to both time and costs
- Non-excusable, because the contractor should have anticipated design changes
- Concurrent, because the contractor could have worked on other activities
- Excusable and non-compensable, because it is beyond either party's control
Show answer & explanation
Correct answer: A - Excusable and compensable, entitling the contractor to both time and costs
Question 7
Two critical path activities are candidates for crashing:
• Activity X: Normal Duration = 14 days, Crash Duration = 10 days, Normal Cost = $28,000, Crash Cost = $40,000
• Activity Y: Normal Duration = 10 days, Crash Duration = 7 days, Normal Cost = $15,000, Crash Cost = $27,000
To reduce the project duration by 3 days at the lowest additional cost, which activity should be crashed first?
- Activity Y, because it has a shorter crash duration
- Activity X, because it offers more total crashable days
- Activity X, because its crash cost slope is lower
- Activity Y, because its normal cost is lower
Show answer & explanation
Correct answer: C - Activity X, because its crash cost slope is lower
Question 8
A scheduler needs to resolve a resource over-allocation where two critical activities require the same crane during the same week. The project completion date is contractually fixed and cannot be extended. Which technique is MOST appropriate?
- Resource leveling
- Fast-tracking the over-allocated activities
- Resource smoothing
- Adding a second crane or shifting one activity to available float on a non-critical path
Show answer & explanation
Correct answer: D - Adding a second crane or shifting one activity to available float on a non-critical path
Question 9
During a monthly schedule update, the scheduler discovers that Activity F has started even though its predecessor, Activity E, is only 60% complete. The original logic is E → F (Finish-to-Start). If the scheduling software is set to Retained Logic, what will happen to the remaining duration of Activity F?
- The software will automatically convert the FS relationship to a Start-to-Start
- It will be scheduled to continue from its actual progress point without interruption
- The software will flag an error and refuse to calculate the schedule
- The remaining work on F will be delayed until E is complete
Show answer & explanation
Correct answer: D - The remaining work on F will be delayed until E is complete
Question 10
A CPM schedule contains multiple date constraints, including several Must-Finish-On and Finish-No-Later-Than constraints imposed by the contract. The scheduler notices that the lowest-total-float method identifies a different critical path than the longest-path method. According to AACE RP 49R-06, which method should be used to identify the TRUE driving critical path?
- The longest path method
- Lowest total float, because it is the traditional CPM definition
- Whichever method produces the shorter project duration
- Neither - the scheduler should remove all constraints and recalculate
Show answer & explanation
Correct answer: A - The longest path method